Analysis of the Small Package Container Supply Chain
"25kg + Containerized" PVC Transportation Process
"25kg + Containerized" PVC Transportation Process
-
The client operates three shifts per day, with 35 workers per shift and an 8-hour workday, resulting in a total of 840 working hours daily (35 workers × 8 hours × 3 shifts = 840 working hours).
-
For the downstream client
-
Regarding factory unloading operations, 4 workers can finish unloading 17 tons of materials within half an hour. Therefore, the total working hours needed for 2,800 tons of materials is calculated as follows: 2,800 ÷ [(17 tons × 2) ÷ 4 workers] = 330 working hours.